Here is what will be happening this week during the Highway 23 construction project in downtown Darlington: at the bridge & River Street intersection, crews will finish grading gravel at the intersection today (Monday). Asphalt paving is scheduled for Tuesday. On Thursday, a temporary traffic signal is scheduled to be turned on and traffic switched to one lane access across the bridge. Expect delays during this time. The Bridge crew is scheduled to mobilize a crane. A temporary concrete barrier wall and other equipment will start demolition the following week, beginning Monday May 24th. Highway 23 flagging will take place from 8am-7pm and will continue until the temporary signal is operational. County Highway F and East River Street will remain closed until the temporary signal is operational. Cornelia Street will be closed when Louisa Street is re-opened. Alice Street will remain closed.